Chris Dant Master Project
Basic Pipeline
Stage
Progress
Time Spent
Planning Poker Numbers
Slice - creates line segments (unordered)
Done
2.5 weeks
10
Contour Generation (orders the line segments and fixes up the contour gaps)
In Debug stage
5 weeks
3
Perimeters - interior contours to thicken the wall
Next
?
5
Infill - make the layer solid
Not done
?
10
G-Code generation - output for printer
Not done
?
10